Report meter events summary ETL task

The ReportMeterEventsSummary ETL Task populates the ReportMeterEventsSummary datamart table. The Web-based Meter Events Summary report runs against this table to identify all meter events for all service points within a specified date range. This task provides the ability to schedule, execute, and monitor the ETL process via the IEE task system.

Create a schedule to execute this task daily after reading data is received and the validation and estimation processes have had time to complete. (System Operations > Recurring schedules overview.)

Use the following procedure to configure a task template:

  1. Go to System Operations > Task Management > Task Templates.

  2. Use the dropdown menu to select the Task Type and Task Template. (Click Add to create a new task template. For more information, see Adding task templates.)

  3. Configure the Task specific parameters. These parameters are defined after step 5 of this procedure.

  4. Configure the Common task template parameters. For more information, see Task template parameters.

  5. Click Save.

Task Specific Parameters:

ClosedFull ETL

See also No usage at active report.