Peak events

Use Peak Events to add, delete, and view events.

Adding a Peak Event

  1. Go to System Administration > System Administration > Peak Events

  2. Right-click Peak Event Definitions.

  3. Select Add Peak Event.

  4. Assign a unique name for the Peak Event ID.

  5. Under Event Start Time, select a date from the dropdown list. This is the event start date.

  6. Under Event End Time, select a date from the dropdown list. This is the event end date.

    Tip: The Peak Event start and end times are only for the What If Analysis Report. These times are not used for curtailment.

    Note: The Event Start Time and Event End Time must have matching calendar days.